REAL ESTATE AND CONSTRUCTION LAW

Construction in Return for Land Share Contract

A construction in return for land share contract carries both a works element and a promise to sell an immovable; this hybrid structure makes it uncertain which provision applies when a dispute arises. The care taken when the contract is formed determines everything that follows.

A construction in return for land share contract contains an undertaking to transfer a share at the land registry, so it must be made in official form, as a notarial deed drawn up by the notary (düzenleme); a contract in ordinary written form is as a rule invalid. If the developer is in default on delivery, the landowner may claim delay compensation; for defective performance, repair or a price reduction; and in serious cases termination of the contract. Where construction is substantially complete, the courts prefer termination with prospective effect over termination with retrospective effect.

Character of the contract and the form requirement

A construction in return for land share contract combines two separate obligations: the developer's obligation to carry out the construction (contract for works) and the landowner's obligation to transfer the land share (promise to sell an immovable). Because it contains an undertaking to transfer an immovable, the contract must be made as a notarial deed drawn up by the notary (düzenleme). Contracts made in handwriting or merely certified by a notary (onaylama) are as a rule invalid.

In practice, where construction has been completed and the flats delivered despite an invalid contract, the courts may find it contrary to the principle of good faith to plead invalidity, taking into account that the parties acted in accordance with the contract for a long time. But this does not make it reasonable to start work with an invalid contract: that debate itself means a case lasting years.

What the contract must contain

  • Delivery date and the sanction to apply in case of delay (delay compensation, rent)
  • Allocation table: which independent unit will belong to whom, specifying floor and facade
  • Technical specifications: the quality of the materials to be used, brand or equivalent quality definition
  • Stages of the land share transfer: how much share will be transferred at which level of construction
  • Who is responsible for the permit, the occupancy permit and public obligations
  • Whether the developer may assign the contract

Transferring the whole land share at the outset is the riskiest structure for the landowner. Gradual transfer of shares tied to the level of construction is the balanced solution that protects both the landowner and the financing.

Delay and default

If construction is not finished on the delivery date, the main items the landowner may claim are these: delay compensation if agreed in the contract, and if not agreed, the rental value of the undelivered independent units (lost income). The rent is determined by a court-appointed expert according to comparable rents.

Defective performance

Where the work is defective, inspection and timely notification are important; hidden defects must be notified without delay after discovery (TBK Arts.474–477). Subject to the conditions in Article 475, remedies include repair, price reduction or rescission, together with damages where fault exists. They are not universally sequential. Restrictions on rescission for structures on the employer’s land apply. Under Article 478, the period for immovable works is five years from delivery, and twenty years where the contractor is grossly at fault.

Evidence of the defect should be preserved before alterations. Judicial preservation of evidence may be useful but is not a universal prerequisite for asserting a claim; it must not delay the necessary defect notice.

Termination

If the developer has not built at all or has left the construction at a very low level, termination of the contract comes into question. The decisive criterion here is the completion ratio of the construction. Where construction is substantially complete, the courts prefer termination with prospective effect, in which what has been done up to that point is preserved, over treating the contract as never made (termination with retrospective effect). Otherwise third parties who bought completed independent units would suffer.

Flats sold to third parties are the most complex side of these files: the buyers are mostly in good faith, and their claims for title transfer conflict with the landowner's claims.

For general information purposes; every contract is assessed on its own text.

FREQUENTLY ASKED

What people ask about this area

The developer delivered the flats late, what can I claim?
If delay compensation was agreed in the contract, you may claim that directly; if not, you may claim the comparable rental value of the undelivered independent units. The period claimed is the period between the agreed delivery date and the actual delivery date. If the defence is raised that the delay was caused by force majeure, that is assessed separately.
Our contract is not notarised, it is in ordinary written form. Is it valid?
Contracts containing an undertaking to transfer land share must be made in official form, as a notarial deed drawn up by the notary; a contract in ordinary written form is as a rule invalid. However, if construction is substantially complete and the parties have acted in accordance with the contract for a long time, pleading invalidity may be found contrary to the principle of good faith. This assessment is specific to the file and is not something to rely on from the start.
There is a construction defect in my flat, what should I do?
Inspect the work and notify the contractor of defects within the applicable periods under Articles 474–477 TBK. Preserve photographs, correspondence and other evidence; judicial preservation of evidence may be useful where the condition may change, but it is not a mandatory first step or condition of suit. Depending on Article 475 and the circumstances, remedies include free repair, price reduction or rescission, together with damages where the conditions are met.
What happens if the contract is not notarised?
Because it contains an undertaking to transfer a share at the land registry, the contract must be made as a notarial deed drawn up by the notary; a contract in ordinary written form is as a rule invalid. On the other hand, where the obligations have been substantially performed, pleading invalidity may be held contrary to the principle of good faith.

If your question is not hereContact

IMPORTANT NOTICE

This page is general information only and does not constitute legal advice. Every file is assessed on its own documents, dates and parties; the general explanations here cannot be applied directly to your own situation. Prepared in line with the Union of Turkish Bar Associations’ advertising restrictions. This English text is a courtesy translation prepared by the firm; in case of any discrepancy the Turkish text prevails.

Write on WhatsApp